THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek., This news data comes from:http://www.yamato-syokunin.com
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.

The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- BIR to audit contractors flagged for ghost flood projects for tax fraud — BIR
- Escudero subpoenaes 10 DPWH contractors for Senate probe next week
- MMDA unveils plan to build rainwater impounding facilities in Camp Aguinaldo
- NBI slaps Alice Guo, 35 Others with new graft, misconduct cases
- Putin vows not to back down in Ukraine
- DPWH engineer denies role in Bulacan flood control ‘ghost projects’
- Motive probed for US shooting that killed two children, injured 17
- Philippine forces deliver supplies and personnel to disputed South China Sea shoal despite tensions
- Villanueva: Regularize contractual govt workers
- LGBTQ+ Catholics make Holy Year pilgrimage to Rome and celebrate a new sense of acceptance